QLD GUIDE

Payment claims under Queensland's BIF Act: a subcontractor's practical checklist

How to prepare, serve and track payment claims under Queensland's Building Industry Fairness (Security of Payment) Act 2017, written as a working checklist for subcontractors.

Built by Tender Ready Tools, a Queensland-based engineer working in HV/LV project delivery. Published 30 October 2026 ยท 7 min read

Items marked verify refer to legislation or regulator guidance that changes over time. Check the linked official source before relying on them.

Getting paid for work done is the whole point, yet many Queensland subcontractors lose leverage through small administrative slips: a claim sent to the wrong address, a deadline missed by a day, or a payment schedule that nobody read closely. The Building Industry Fairness (Security of Payment) Act 2017 (the BIF Act) verify gives subcontractors a statutory right to progress payments and a fast adjudication process. Those rights depend on getting the paperwork right.

This checklist is for subcontractors on commercial building, civil and industrial electrical projects in Queensland. It is general information, not legal advice. Timeframes and requirements in the Act and your contract can change and interact in complicated ways, so every time limit below is marked verify. Check the current Act, the QBCC's commercial payment dispute guidance, and get advice for anything significant.

Before the first claim: set up the job

Most payment disputes are decided by what happened in the first two weeks of a job. Before you start work:

What a valid payment claim must contain

Under the BIF Act, a payment claim generally needs to do three things verify:

  1. Identify the construction work (or related goods and services) the claim relates to.
  2. State the amount of the progress payment you claim is payable.
  3. Request payment of that amount.

Earlier versions of Queensland's security of payment rules required a statement that the claim was made under the Act. Amendments changed this, so an invoice can now operate as a payment claim if it meets the requirements verify. Many subcontractors still include a short statement for clarity; it does no harm.

Practical checklist for each claim:

For electrical and HV/LV packages: attach progress evidence that a non-electrical commercial manager can follow. Cable schedules with metres installed and terminated, a list of switchboards or RMUs set and tested, and signed ITP sheets make it much harder to argue that work isn't complete.

Timing: when you can claim and how late is too late

The payment schedule: read it the day it arrives

If the head contractor (the respondent) intends to pay less than the claimed amount, it must give you a payment schedule within the time allowed by the Act or the contract, whichever is shorter verify. The schedule must state the amount it proposes to pay and, if less than claimed, the reasons verify.

When payment doesn't arrive: your options

If you aren't paid the scheduled amount by the due date, or the schedule is less than you claimed, the BIF Act provides several routes verify. Which suits depends on the amount, relationship and evidence.

  1. Talk first, in writing. A short email that references the claim, the schedule and the due date often fixes administrative delays.
  2. Adjudication. A fast, interim process through the QBCC's adjudication registry. You must apply within strict time limits after receiving the schedule or after the due date passes verify. See the QBCC's how to apply for adjudication page.
  3. Recovery as a debt in court for unpaid amounts in some situations verify.
  4. Suspending work after giving the required notice, where payment has not been made verify. Get advice before suspending; getting it wrong can put you in breach.
  5. Payment withholding requests, which can require a higher-tier party to withhold money owed to the head contractor in some circumstances verify.

The adjudication time limits are short and are measured in business days. Count them carefully against Queensland public holidays and the Christmas shutdown period, which the Act may treat differently verify.

Preparing an adjudication application

If you go down this path, the quality of your evidence matters more than the strength of your feelings. Most of it should already exist if you followed the setup steps above:

Many subcontractors use a lawyer or claims consultant for adjudication, particularly for larger amounts. Even if you do, having this file organised saves fees and time.

Common mistakes that cost subcontractors money

A simple monthly routine

  1. Two days before the reference date: update quantities and collect evidence.
  2. On the reference date: issue the claim, save proof of service, update the register.
  3. When the schedule arrives: compare, note reasons, respond in writing to anything unclear.
  4. On the due date: check payment received and reconcile.
  5. If anything is short: decide your next step well before the time limit closes.

Payment claims are one part of being a well-run subcontractor. If you'd like to see how the rest of your business paperwork stacks up, including licensing, insurance, WHS, quality and contract admin, try the free Subcontractor Readiness Scorecard. For prequalification specifically, see our QBCC prequalification checklist.

This guide is general information only, not legal advice. The BIF Act and its regulation are amended from time to time, and your contract terms matter. Check every item marked verify against the current Act on legislation.qld.gov.au and QBCC guidance, and seek legal advice for disputes.