Red flags in subcontract terms: a Queensland subcontractor's pre-bid checklist

Most subcontract pain is written into the terms before you ever price the job. This checklist walks through the clauses worth reading first, why they hurt, and what you can do about them while you still have leverage: before the bid goes in.

Built by Tender Ready Tools, a Queensland-based engineer working in HV/LV project delivery. Published 30 October 2026 ยท 7 min read

Items marked verify refer to legislation or regulator guidance that changes over time. Check the linked official source before relying on them.

A tender package lands on Thursday afternoon, closing the following Wednesday. The drawings and scope get most of the attention, and the subcontract terms get a skim on the last night. That is backwards. Your rates are only as good as the terms they sit under. A sharp price on a contract with uncapped liability, open-ended liquidated damages and a two-day notice bar is not a sharp price. It is a bet.

This checklist is written for Queensland subcontractors in building, civil and industrial electrical work, including HV/LV. It is general information drawn from project practice, not legal advice. The law changes and every contract is different, so treat each regulatory point marked verify as a prompt to check the current official source and, where the dollars justify it, get advice before you sign.

Why read the terms before you price

Once you are the preferred tenderer, your leverage drops fast. The head contractor has carried your number into its own bid, the program is locked and the conversation becomes "we can't change the head contract terms now." Before submission you can still do three things: price the risk, qualify it in your offer, or walk away. After award, you mostly just carry it.

A practical habit: give the subcontract a 45-minute read on day one of the tender, with a highlighter and the list below. Anything that hits a red flag goes to the estimator and the person signing off the bid, not to a note at the bottom of the email.

1. Liquidated damages and delay exposure

What to do: price a realistic delay allowance, ask for a cap (commonly expressed as a percentage of subcontract value) and qualify that LDs are the sole remedy for delay.

2. Liability, indemnities and consequential loss

3. Payment terms and security of payment

Queensland has strong security of payment laws, but contracts still contain terms that test them. Under the Building Industry Fairness (Security of Payment) Act 2017 verify, a "pay when paid" provision in a construction contract has no effect. The Act's notes also point to the QBCC Act 1991 verify, under which a provision in a subcontract for payment of a progress payment later than 25 business days is void.

For the claim side, see our BIF Act payment claims checklist.

4. Security, retentions and bank guarantees

The QBCC Act verify sets a condition that, before practical completion, the total of retentions withheld and securities held under a subcontract is not more than 5% of the subcontract price, with some exceptions. Read the security clause with that in mind.

5. Design responsibility and scope creep

6. HV/LV and industrial electrical specifics

Industrial electrical packages carry risks that general building subcontracts often ignore. Electrical work in Queensland sits under the Electrical Safety Act 2002 verify, and the Electrical Safety Office verify publishes guidance, but the contract decides who carries the commercial risk.

7. Changes, notices and time bars

Variation and claim clauses decide whether you get paid for extra work. Short notice periods, strict forms and "no notice, no claim" wording can wipe out valid entitlements. This one is big enough to have its own guide: time bars and notices in subcontracts: what to track.

8. Termination, suspension and disputes

Price it, qualify it, or walk away

Each red flag has three answers. Some risks you can price: a realistic delay allowance, extra supervision or a contingency against a long-lead item. Some you should qualify: a clear, specific departure in your offer such as "liability capped at 100% of subcontract value" or "LDs capped at 10% of subcontract value and sole remedy for delay." And some you should treat as a hard stop: if an uncapped liability clause or an unworkable payment chain will not move, the honest answer may be not to bid.

Keep qualifications short and specific. A page of vague exclusions tends to get ignored or scored down. Five precise departures, each tied to a clause number, get read.

If you want to turn this checklist into a number, the {https://tenderready0.gumroad.com/l/yrppp} tool walks through 41 red-flag checks, scores likelihood and consequence, and drafts a qualifications list for your offer. It is a decision aid, not legal advice.